Project Connect leaders break down 5 light rail options, future buildout opportunities

AUSTIN (KXAN) — After Project Connect leaders debuted five reduced light rail scope options last month, officials spoke Thursday on how the system will be built out in the future.

The two-hour community meeting featured engagement opportunities between the public and program leadership. Some questions from the public highlighted concerns with the narrowed vision behind the light rail scope — initially presented to voters as two light rail lines, the Blue and Orange lines.

Thursday evening, officials said the decisions to come this June won’t encompass the totality of all future light rail in Austin; rather, they called it the jumping off point for future buildout.

Each of the five options will incorporate opportunities for future connections north, south and east, they added.

“It will allow us to build out the full vision that you also voted for over time. That’s the plan,” said Peter Mullan, executive vice president of architecture and urban design for the project. “What we’re talking about now, I think, is ‘what is the first piece that we should be building?'”

Austin Transit Partnership has unveiled five options for Project Connect’s light rail system. (Courtesy: Austin Transit Partnership)Austin Transit Partnership has unveiled five options for Project Connect’s light rail system. (Courtesy: Austin Transit Partnership)Austin Transit Partnership has unveiled five options for Project Connect’s light rail system. (Courtesy: Austin Transit Partnership)Austin Transit Partnership has unveiled five options for Project Connect’s light rail system. (Courtesy: Austin Transit Partnership)Austin Transit Partnership has unveiled five options for Project Connect’s light rail system. (Courtesy: Austin Transit Partnership)

Officials said project leaders are incorporating feedback from the public through May 2 before an official decision is made on the initial investment. Some of the considerations being weighed through this project include:

Estimated average daily passengers on each route

Community demographics of areas served

Connectivity with key destinations in Austin

Equitable distribution of resources

Annick Beaudet with the City of Austin said the selection process includes both planning for current transit riders within CapMetro’s system, as well as projecting and anticipating future ridership. As part of the city’s Strategic Mobility Plan, she said land use development and building more compact, walkable centers will help support mass transit growth.


RELATED: Project Connect debuts 5 scaled down light rail options

Some members of the public noted differences between the current options versus the initial conceptual map shown to voters for the past two-and-a-half years. Part of those changes reflected in the latest design considerations were made to minimize the overall costs of this first investment.

Right now, all five options on the table are estimated at approximately $5 billion.

Lindsay Wood with the Austin Transit Partnership added its integral Project Connect is “good stewards” to the tax dollars voters approved in the November 2020 election, while also maximizing the federal dollars the project can receive via grants and other funding opportunities.

This comes after the city announced in late February its partnership with the U.S. Department of Transportation to help fund transportation initiatives, including Project Connect. Wood said Thursday project leaders anticipate roughly half of the light rail’s costs will be funded via federal dollars.

Those wanting to review the light rail options can find them online. To give feedback, you can upload them online, email your comments to input@atptx.org or mail them physically to ATP at 203 Colorado St., Austin.

 

Project Connect officials have whittled the system down to five scope options, variations that primarily include street-level light rail services. (Photo: Avery…

Project Connect officials have whittled the system down to five scope options, variations that primarily include street-level light rail services. (Photo: Avery Travis/KXAN)

AUSTIN (KXAN) — After Project Connect leaders debuted five reduced light rail scope options last month, officials spoke Thursday on how the system will be built out in the future.

The two-hour community meeting featured engagement opportunities between the public and program leadership. Some questions from the public highlighted concerns with the narrowed vision behind the light rail scope — initially presented to voters as two light rail lines, the Blue and Orange lines.

Thursday evening, officials said the decisions to come this June won’t encompass the totality of all future light rail in Austin; rather, they called it the jumping off point for future buildout.

Each of the five options will incorporate opportunities for future connections north, south and east, they added.

“It will allow us to build out the full vision that you also voted for over time. That’s the plan,” said Peter Mullan, executive vice president of architecture and urban design for the project. “What we’re talking about now, I think, is ‘what is the first piece that we should be building?’”

Austin Transit Partnership has unveiled five options for Project Connect’s light rail system. (Courtesy: Austin Transit Partnership)Austin Transit Partnership has unveiled five options for Project Connect’s light rail system. (Courtesy: Austin Transit Partnership)Austin Transit Partnership has unveiled five options for Project Connect’s light rail system. (Courtesy: Austin Transit Partnership)Austin Transit Partnership has unveiled five options for Project Connect’s light rail system. (Courtesy: Austin Transit Partnership)Austin Transit Partnership has unveiled five options for Project Connect’s light rail system. (Courtesy: Austin Transit Partnership)

Officials said project leaders are incorporating feedback from the public through May 2 before an official decision is made on the initial investment. Some of the considerations being weighed through this project include:

Estimated average daily passengers on each route
Community demographics of areas served
Connectivity with key destinations in Austin
Equitable distribution of resources

Annick Beaudet with the City of Austin said the selection process includes both planning for current transit riders within CapMetro’s system, as well as projecting and anticipating future ridership. As part of the city’s Strategic Mobility Plan, she said land use development and building more compact, walkable centers will help support mass transit growth.


RELATED: Project Connect debuts 5 scaled down light rail options

Some members of the public noted differences between the current options versus the initial conceptual map shown to voters for the past two-and-a-half years. Part of those changes reflected in the latest design considerations were made to minimize the overall costs of this first investment.

Right now, all five options on the table are estimated at approximately $5 billion.

Lindsay Wood with the Austin Transit Partnership added its integral Project Connect is “good stewards” to the tax dollars voters approved in the November 2020 election, while also maximizing the federal dollars the project can receive via grants and other funding opportunities.

This comes after the city announced in late February its partnership with the U.S. Department of Transportation to help fund transportation initiatives, including Project Connect. Wood said Thursday project leaders anticipate roughly half of the light rail’s costs will be funded via federal dollars.

Those wanting to review the light rail options can find them online. To give feedback, you can upload them online, email your comments to input@atptx.org or mail them physically to ATP at 203 Colorado St., Austin.

Copyright 2023 Nexstar Media Inc. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed.

<article class="article-list__article" data-article-id="1712599" data-context="headline_list_one_col_image_branded" data-index="0" data-collection="article-list1" data-anvato-params=""pauseOnTabInactive":false
// –>

Tracking the Coronavirus


What is the current COVID risk in your county?

/ 11 hours ago

Austin Weather

Current

50°

Light Rain with Thunder

Tonight

49°

Thunderstorms

Precip: 90&percnt;

Tomorrow

54°

Thunderstorms

Precip: 90&percnt;

Trending Stories


Expert says Daniel Perry slowed down during turn


Report: AUS executive director had conflict of interest


Heaviest rain in 8 months continues


Two new tiny homes unveiled at Community First! Village


What caused the giant seaweed blob?

Don’t Miss


KXAN’s beloved Kaxan dies after brain cancer battle


VOTE: Help us choose the best viewer photo of March


Which areas of Texas are growing the fastest?


2023 already off to a record start at Austin airport


KXAN launches new news podcasts



Latest weather conditions from the KXAN First Warning Weather team